| |
Ferries funded in 2003 still
have not been built or designed
New ferries
were scheduled for 2008 delivery
During the recent special
legislative session, regularly scheduled committee work continued aside
from the primary focus of state lawmakers to reinstate Initiative 747.
The Joint Transportation Committee held a hearing on November 28 to
discuss the failure of the state to build four new ferries approved in
2003. The following is an exchange between
Deputy Republican Leader Rep. Doug Ericksen
and state Transportation Secretary Paula Hammond on the issue.
Ericksen: "In 2003, when we passed the Nickel Package [gas
tax increase], we put $285 million into four new ferry boats – and the
first one was to be delivered in 2008 with the finish of that by 2010.
Now here we are in 2007, 2008 coming up, and my understanding is we are
still in design phase?"
Hammond: "We are nearing design phase…"
Ericksen: "Nearing…what happened?"
Hammond: "The consortium…last year you passed a law that agreed
we could because we were having trouble finding a procurement process
that was going to work. We have a lawsuit pending, we have been plagued
with lawsuits on this procurement process, um, and we have also had the
problem with, uh, when we did our financial screening of the eligible
Washington builders in a build it in Washington program, we were faced
with one bidder. And that is why we came back to you last year and asked
for a different kind of opportunity for a procurement process which you
granted, um, and we are now working with a consortium of boat builders,
Todd, Nichols and Martinac, to build up to four 144’s. And I am saying
that now because as I look at our financial situation, we are really
questioning whether we can afford three or four, um, but we are, uh, we
have terms and agreements for the first phase of the contract ready to
go. I have not signed it yet with recent events we are questioning how
we’re going to move forward, but our intent is to move forward with that
design process, uh, and get I think the first boat delivered by 2010?
Steve, is that the path we are on? Summer of 2010?"
Ericksen: "Is the $285 million still
there?"
Hammond: "Yes…well it, it, yes. I hesitate because some of that
money has been spent as we moved into the procurement of the, um,
propulsion systems and some pre-design work we’ve done."
Ericksen: "Should we be able to get
the ferries done quicker now...was it phased-in money before so there
was a time lag?"
Hammond: "There was a cash flow…"
Ericksen: "So now we should be able
to get it all done right away?"
Hammond: "Uh, what do you mean? I’m not sure…"
Ericksen: "You had a cash-flow issue
for the first four, but since those are supposed to have been done by
2008, shouldn’t the money now be available so those should be
constructed quicker?"
Hammond: "In the 07 budget we adjusted the cash flow based on the
path we’re on now. But one of the questions we’re asking ourselves is,
if we now need to build two or yesterday’s concept of three smaller
steel-electric replacements, if we need to do that and the time, uh,
issue is so prevalent, do we move those ahead or how do we insert them
in a cash flow way, uh, to the other procurement process? So those are
the questions we are asking right now."
Statement from Rep. Doug Ericksen:
"In 2003, I helped
construct and voted for a transportation budget that included funding
for four new car ferries to replace our aging boats. Those ferries were
supposed to be online beginning in 2008. The state Department of
Transportation has failed – and the current leadership in Olympia has
failed. It is vital that the state start regaining the trust of the
people by keeping the promises it has made."
Timeline for ferry
problems
-
April 27, 2003 –
Legislature passes Nickel Package gas tax increase with $285 million
to replace the four Steel Electric boats. The first vessel is
scheduled for delivery in October 2008.
-
Dec. 3, 2003 –
Washington State Ferries (WSF) issues Request for Proposal for
prequalification to build four new ferries.
-
Feb. 11, 2005 – WSF
disqualifies Martinac from bidding on the vessel construction
contract.
-
Feb. 18, 2005 –
Martinac appeals disqualification.
-
June 1, 2005 – State
Administrative Law Judge rules in favor of Martinac and says the
state should not have disqualified the company from bidding.
-
June 22, 2005 – State
appeals judge’s ruling.
-
Sept. 17, 2005 – State
reverses itself and does not act on the appeal. Martinac is allowed
to bid on the contract.
-
March 8, 2006 –
Legislature passes Supplemental Transportation Budget increasing the
size of the four boats from 133 to 144 cars. Costs increase by $13.8
million.
-
April 21, 2007 –
Legislature passes 2007-09 Transportation Budget. Costs to build the
four boats increases $25.7 million and delivery of the first boat is
delayed until 2010.
-
Sept. 27, 2007 – WSF
says $3.6 million spent on emergency repairs for Steel Electrics.
-
Oct. 27, 2007 – WSF
plans for the new boats call for not replacing two Steel Electric
vessels (contrary to the original plan).
-
Nov. 20, 2007 – WSF
orders all four Steel Electric vessels tied up, shutting down
service on the Port Townsend - Keystone route.
-
Nov. 21, 2007 – Gov.
Gregoire says lawmakers need to make replacing the four 80-year-old
ferries a top priority.
|
Milestones
Source: 2006 Ferry Finance Study and Office of Program
Research |
| |
2003 |
2004 |
2005 |
2006 |
2007 |
Total |
% (03-07) |
| # of new vessels planned |
4 |
4 |
5 |
4 |
4 |
|
|
| Funding |
284.7 |
284.9 |
351.3 |
321.9 |
347.6 |
|
|
| Major Changes |
| Add
one vessel (TPA fund) |
|
|
66.4 |
|
|
|
|
|
Increase size to 144 vehicles |
|
|
|
24 |
|
|
|
| Cost
increases |
|
0.2 |
|
13.8 |
25.7 |
|
|
|
Remove fifth vessel |
|
|
|
-67.2 |
|
|
|
| Change in funding |
|
0.2 |
66.4 |
-29.4 |
25.7 |
62.9 |
22% |
# # #
For more information, contact:
John
Handy, Assistant Director: (360) 786-5758
|
|